Delivery timeline

Work back from the date the unit has to be in service.

HLE delivers most units 3 to 6 months after the signed order, deposit and chassis; trailers 3 to 4 months after the signed order, deposit and trailer. Most of the market quotes a year or more for a ground-up build; HLE has delivered a high-priority unit in about 80 days from purchase order to finished unit. Pick the vehicle, enter the date you need it by, and you get the date the order, deposit and chassis have to be in. The proposal carries the dated schedule for your unit.

Your dates

Grant performance date, program launch, or the day it has to be in service.
HLE lead time
3 – 6 months
3 to 6 months after the signed order, deposit and chassis.
Order, deposit and chassis in by
Pick a date
At the short end
—

What happens inside those days

From the signed order, deposit, chassis and drawing to delivery: 90 days (3 months) at the short end, 180 days (6 months) at the long end. A typical build does not run past 6 months.

#StageDays
0Order, deposit, chassis and signed drawing
Engineering sign-off comes first; then the signed order, the deposit, the chassis and the signed drawing land together and the clock starts. Chassis supply is the usual variable; HLE keeps chassis inventory on hand to shorten it.
Day 0
1Body and structure
The steel cage is welded and powder-coated, then insulated and skinned: sidewalls, roof and floor go on station by station, and the body is painted. This is the part of the build that decides how the unit holds up in year ten.
30 – 55 days
2Interior and equipment
Cabinetry, electrical harnesses and panels, HVAC, plumbing, the equipment your program runs on, and the interior finish. Graphics go on inside these days.
45 – 97 days
3Rain test, road test and delivery
Fifteen minutes minimum in the rain booth with a person inside, a road test with hard braking and acceleration, the final inspection packet, then the walkthrough, panel drawings and warranty registration.
15 – 28 days
Delivered90 – 180 days

Stage days are planning figures: the share each stage takes of HLE's lead time. The bar shows each stage on one scale, 0 to 180 days: solid to the short end, light to the long end.

A dated schedule

Tell us the date. The proposal comes back with your dates filled in.

Grant deadlines and launch dates are common in this work. Send the date with the plan you are looking at and we schedule backward from it, chassis first.